The construction market in Asia Pacific is forecasted by GlobalData to grow by 3.7% in real terms in 2023, having grown by 3.9% in 2022. A key growth market will be the infrastructure market, with output rising by 11.9% in real terms. GlobalData tracks and profiles all major construction projects from announcement to completion. For further insight on this market, buy the latest profiles here.

Here are Asia Pacific’s five largest coal construction projects that were initiated in Q4 2023, according to GlobalData’s construction projects database.

Smarter leaders trust GlobalData

Report-cover

Premium Insights Construction Project Profiles

Buy the profiles

Premium Insights

The gold standard of business intelligence.

Find out more

1. Jiaxing Coal-Fired Power Plant Expansion Phase IV

The project involves the construction of a coal-fired power plant in Jiaxing, Zhejiang.China.

Construction work started in Q4 2023 and is expected to be completed in Q4 2027.

The project aims to enhance power generation capacity and improve the coal ecological environment in the region. Buy the profile here.

2. Shangrao Coal-Fired Power Plant

The project involves the construction of a coal-fired power plant with a capacity of 2,000MW in Shangrao, Jiangxi, China.

Construction work commenced in Q4 2023 and is expected to finish in Q4 2025.

The project aims to increase power generation capacity to meet the region’s growing demand.

3. Xiwangzhai Coal Fired Integrated Power Plant 1320 MW

The project involves the construction of a coal-fired integrated power plant in Fugu County of Yulin, Shaanxi, China.

Construction work started in Q4 2023 and is forecast to complete in Q1 2027.

The project aims to enhance power generation capacity, and improve the coal ecological environment in the region.

4. Manglai Coal-Fired Power Plant 1320 MW

The project involves the construction of a coal-fired power plant in Bayan Ulasumu, Sunit Left Banner, Xilingol League, Inner Mongolia, China.

Construction work commenced in Q4 2023 and is expected to be completed in Q4 2025.

The project aims to increase electricity generation capacity to meet the region’s growing demand.

5. Fuzhou Thermal Power Plant Phase II 1320MW

The project involves the construction of a coal-fired power plant in Fuzhou, Fujian, China.

Construction work started in Q4 2023 and is expected to be completed in Q3 2025.

The purpose of the project is to increase electricity generation capacity to meet the region’s growing demand. Buy the profile here.

For more details on the latest construction projects, buy the profiles here.

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

GlobalData’s Construction Projects database tracks over 220,000 new construction projects valued at >$25m from announcement to completion across all countries and sectors.