A 1 Lohne Bramsche, a joint venture (JV) between Johann Bunte Bauunternehmung and STRABAG has secured a €600m contract to widen nearly 30km on the A1 motorway in Lower Saxony, Germany.

The function-based construction (FSB) contract was awarded by Die Autobahn GmbH des Bundes, representing the Government of Germany to widen a road stretch between Lohne/Dinklage and Bramsche.

The project is expected to begin from February 2021 and will include widening from two lanes to three lanes in each direction.

Under the joint venture, Johann Bunte will be the technical lead for the project, while Strabag will take the commercial lead.

The motorway will remain open for traffic during the whole construction period and it is expected to be completed by mid-2025. The contract also includes structural maintenance over the next three decades.

The project includes extensive earthworks and construction of carriageways. Also, 14 bridges along the motorway section and two overpasses over the motorway must also be rebuilt completely, along with the rehabilitation of 18 bridges.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The JV plans to complete the project in eight phases. The first five phases will include widening of the motorway in the direction of Osnabrück between 2021 and 2022.

The last three phases will include widening and new construction work in the direction of Bremen.

Strabag CEO Thomas Birtel said: “The widening of the motorway from four to six lanes will eliminate a bottleneck on the busy A1.

“We are pleased to be able to contribute our expertise as the market leader in German transportation infrastructure construction to this major project.”

Johann Bunte Bauunternehmung management spokesman Manfred Wendt said: “With this contract, we are continuing our long-standing tradition and expertise in the realisation of infrastructure projects of this magnitude.

“Thanks to its excellent local knowledge and wealth of experience in motorway construction and civil engineering, BUNTE is in a strong position to accomplish these demanding tasks.”

—————————————————————————————————————————————-

The 30km A1 motorway contract includes widening of two lanes to three lanes in each direction. (Credit: STRABAG.)