Finnish transmission system operator Fingrid has chosen technical solutions provider Caverion to construct the Siuntio substation project in the Helsinki region of Finland.

The estimated value of the project, which is expected to boost the operational reliability of the electricity network, is approximately €10m.

Fingrid project manager Ville-Petteri Haljala said: “We are building, renewing, and expanding substations in the Helsinki region and thus securing a reliable electricity supply.

“The project is also important for Microsoft’s data centre in Vihti, as it will be connected to the Kopula substation with three 110kV connections.”

The current 400/110kV substation’s 110kV switchyard will be expanded as part of the project.

Furthermore, significant changes will be carried out to the existing yard structures in Kopula’s 110kV switchyard. The site’s protection and automation system and its new control centre structure will be replaced.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Caverion Industry division head Elina Engman said: “We recently expanded our expertise by acquiring the substation and power line business of TM Voima in Finland.

“We are proud to offer our solid project expertise to Fingrid, the company responsible for the Finnish main grid.

“Securing electricity supply and the safe distribution of electricity are part of society’s critical functions, and we definitely want to contribute to it.”

The project will commence this month and be completed in January 2026.