Construction work on Refhyne II Renewable Hydrogen Electrolyser 100MW located in Rheinland-Pfalz, Germany commenced in Q3 2024, after the project was announced in Q3 2021. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2027. To learn more about the Refhyne II Renewable Hydrogen Electrolyser 100MW project, buy the profile here.
The project involves the construction of an electrolyzer hydrogen production plant in Rheinland-Pfalz, Germany.
The project includes the following:
1. Construction of an electrolysis facility with a capacity of 100MW and capable of producing 16060 tonnes of hydrogen per year
2. Construction of administrative facilities
3. Construction of substations
4. Construction of a processing unit
5. Construction of power generators
6. Construction of a separation barrier
7. Installation of cooling systems and filters, and the laying of pipelines
Construction on the project is expected to be completed by Q4 2027.
For more details on the Refhyne II Renewable Hydrogen Electrolyser 100MW project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.