Construction work on Mikonkeidas Wind Farm 106 MW located in Finland commenced in Q1 2023, after the project was announced in Q2 2021. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q1 2025. To learn more about the Mikonkeidas Wind Farm 106 MW project, buy the profile here.

The project involves the construction of a 106MW wind farm in Kristiinankaupunki, Ostrobothnia, Finland.

Smarter leaders trust GlobalData

The project includes the following:

1. Construction of a substation
2. Construction of access roads
3. Installation of 16 wind turbines and with each turbine capacity SG 6.6-170 with a height of 145 metres each
4. Installation of transformers and generators
5. Laying of transmission lines

Construction on the project is expected to be completed by Q1 2025.

For more details on the Mikonkeidas Wind Farm 106 MW project, buy the profile here.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.