Construction work on Kotre Basantpur Pachmo Coal Project located in Bokaro, Jharkhand, India commenced in Q1 2023, after the project was announced in Q1 2021. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q1 2027. To learn more about the Kotre Basantpur Pachmo Coal Project project, buy the profile here.
The project involves the construction of a coal-based thermal power plant with generating capacity of 5MTPA at Kotre in Jharkhand, India.
The project includes the following:
1. Construction of water transmission pipeline
2. Construction of raw water treatment
3. Construction of cooling water system
4. Installation of turbines
5. Installation of condenser
6. Installation of boilers
7. Installation of generators
Construction on the project is expected to be completed by Q1 2027.
For more details on the Kotre Basantpur Pachmo Coal Project project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.