Construction work on Isbillen Power Reserve located in Vaesternorrland, Sweden commenced in Q1 2024, after the project was announced in Q1 2023. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q2 2025. To learn more about the Isbillen Power Reserve project, buy the profile here.
The project involves the construction of a 93.9MW battery energy storage system (BESS) on 0.8ha of land in Solleftea Municipality, Vaesternorrland County, Sweden.
The project includes the following:
1. Construction of battery energy storage containers
2. Construction of a substation
3. Construction of access roads
4. Installation of transformers
5. Laying of transmission lines
Construction on the project is expected to be completed by Q2 2025.
For more details on the Isbillen Power Reserve project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.