Construction work on Huangmei Ziyunshan Pumped Storage Power Station 1400 MW located in Huangmei, Hubei, China commenced in Q4 2023, after the project was announced in Q1 2022. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2029. To learn more about the Huangmei Ziyunshan Pumped Storage Power Station 1400 MW project, buy the profile here.
The project involves the construction of a pumped-storage power station with a capacity of 1,400MW at Huangmei County in Huanggang, Hubei, China.
The project includes the following:
1. Construction of powerhouses
2. Construction of substations
3. Construction of headrace tunnels
4. Construction of dams
5. Installation of four 350MW reversible pump turbines and generators
6. Installation of transformers
7. Laying of transmission lines
Construction on the project is expected to be completed by Q4 2029.
For more details on the Huangmei Ziyunshan Pumped Storage Power Station 1400 MW project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.