Construction work on A-Nord HVDC Transmission Line located in North Rhine-Westphalia, Germany commenced in Q4 2023, after the project was announced in Q1 2018. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2025. To learn more about the A-Nord HVDC Transmission Line project, buy the profile here.

The project involves the construction of a 24m wide corridor for a power line of a 300km, 320kV to 525kV high-voltage direct current (HVDC) power line from Emden East and Osterath in Germany.

Smarter leaders trust GlobalData

The project includes the following:

1. Laying of a 23km underground power transmission line from Emden East to Bunde in section A
2. Laying of an 81Km underground power transmission line from Bunde to Wietmarschen in section B
3. Laying of a 93km underground power transmission line from Wietmarschen to Borken/Schermbeck in section C
4. Laying of an 103km underground power transmission line from Borken/Schermbeck to Osterath in section D
5. Installation of transformers

Construction on the project is expected to be completed by Q4 2025.

For more details on the A-Nord HVDC Transmission Line project, buy the profile here.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

GlobalData’s Construction Projects database tracks over 220,000 new construction projects valued at >$25m from announcement to completion across all countries and sectors.