Peab has been commissioned to undertake construction and concrete work at Vinnelys substation in Nordreisa Municipality, Norway.

The contract, worth NOK169m ($15.76m), will be carried out for Statnett.

Commencing operations in 1971, Nordreisa substation serves as a hub in the Northern Network in the country and comprises most of the 132kV network in two counties – Troms and Finnmark.

The current capacity requires an upgrade, mainly because of the developments in the fishing industry and a higher level of electrification.

With regard to the new 420 kV Balsfjord-Skaidi power line, a permit has been given for the new substation at Vinnelys in Nordreisa.

The current substation will be demolished once the new station becomes functional.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The Vinnelys substation will boost capacity in Finnmark and cut down the effect of glitches in the electricity grid.

Peab Norway executive Per Ivar Rasmussen said: “As a local community builder we’re very happy for the opportunity to contribute to more secure electricity delivery to residents and companies in Northern Norway.”

Peab will record the value of this turnkey contract in Q3 2022.

The project will commence in January next year and is expected to complete in February 2024.

—————————————————————————————————————–