Construction work on National Grid-Penang Island Overhead Power Transmission Line located in Perai, Penang, Malaysia commenced in Q4 2023, after the project was announced in Q1 2022. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2024. To learn more about the National Grid-Penang Island Overhead Power Transmission Line project, buy the profile here.

The project involves the construction of an 8.50km overhead power transmission line in Penang, Malaysia

Smarter leaders trust GlobalData

The project includes the following:

1. Construction of the tower foundation
3. Construction of switching stations
4. Construction of controlling units
5. Construction of related infrastructure
6. Installation of tower structures

Construction on the project is expected to be completed by Q4 2024.

For more details on the National Grid-Penang Island Overhead Power Transmission Line project, buy the profile here.

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

GlobalData’s Construction Projects database tracks over 220,000 new construction projects valued at >$25m from announcement to completion across all countries and sectors.