Construction work on Dieppe-Le Treport Offshore Wind Farm 496 MW located in Normandy, France commenced in Q1 2024, after the project was announced in Q1 2007. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2026. To learn more about the Dieppe-Le Treport Offshore Wind Farm 496 MW project, buy the profile here.
The project involves the construction of a 496MW offshore wind farm about 15km off the coast of Le Tréport and 17km off the coast of Dieppe in Haute-Normandie Region, France.
The project includes the following:
1. Construction of a powerhouse
2. Construction of turbine bases
3. Construction of substations
4. Installation of 62 SG 8.0-167 DD offshore wind turbines
5. Installation of electrical feeder systems
6. Installation of converters
7. Installation of electric cables
8. Laying of two 23.5km of 225kV three-core subsea cables
9. Laying of 18km of 225kV single-core onshore cable
Construction on the project is expected to be completed by Q4 2026.
For more details on the Dieppe-Le Treport Offshore Wind Farm 496 MW project, buy the profile here.
Premium Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.