Construction work on the $316m Nusajaya Tech Park Data Center Campus located in Johor Bahru, Johor, Malaysia commenced in Q2 2022. It was announced in Q1 2021.

The project involves the construction of a 22,500m2 data center with a 54MW capacity in Johor, Malaysia.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

The project includes the following:

1. Construction of server rooms
2. Construction of office space
3. Installation of equipment

Construction on the project is expected to be completed by Q3 2026.

Owners of the project include China-based GDS Holdings.