Construction work on Wild Springs Solar Farm 128 MW located in South Dakota, the US commenced in Q1 2023, after the project was announced in Q4 2014. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q2 2023. To learn more about the Wild Springs Solar Farm 128 MW project, buy the profile here.
The project involves the construction of a 128MW solar farm in South Dakota, the US.
The project includes the following:
1. Construction of substation
2. Construction of a maintenance building
3. Construction of a parking lot
4. Construction of three weather stations
5. Construction of access roads
6. Installation of 3,40,000 solar panels
7. Installation of transformers
8. Laying of transmission line
Construction on the project is expected to be completed by Q2 2023.
For more details on the Wild Springs Solar Farm 128 MW project, buy the profile here.