Construction work on the $300m Danville Fully Cooked Poultry Plant located in Danville, Virginia, the US commenced in Q2 2022. It was announced in Q3 2021.

The project involves the construction of a 30,193m2 fully cooked poultry plant in Danville, Virginia, the US.

The project includes the following:

1. Construction of production units
2. Construction of warehouses
3. Construction of distribution units
4. Construction of parking facilities
5. Construction of administrative space
6. Construction of packaging units
7. Construction of cold storage centers
8. Installation of machinery and equipment

Construction on the project is expected to be completed by Q2 2023.

Owners of the project include the US-based Tyson Foods.