Construction work on Gibson Solar Farm 251 MW located in Indiana, the US commenced in Q3 2024, after the project was announced in Q4 2023. According to GlobalData, who tracks and profiles more than 220,000 major construction projects from announcement to completion, the project is expected to be completed by Q4 2026. To learn more about the Gibson Solar Farm 251 MW project, buy the profile here.

The project involves the construction of a 251MW solar farm in Gibson County, Indiana, the US.

Smarter leaders trust GlobalData

Report-cover

Data Insights Arevon - Gibson Solar Farm 251 MW - Indiana

Buy the Profiles

Data Insights

The gold standard of business intelligence.

Find out more

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

The project includes the following:

1. Construction of a substation
2. Construction of a site office
3. Installation of solar panels
4. Installation of inverters
5. Installation of generators and transformers
6. Laying of transmission lines

Construction on the project is expected to be completed by Q4 2026.

For more details on the Gibson Solar Farm 251 MW project, buy the profile here.