Expanding The Karlsruhe-Basel rail corridor from two lines to four is a challenging proposition but as a key trans-European rail corridor it is a necessary one. The line forms part of the vital trade route from Rotterdam in The Netherlands down to Genoa in Italy and adding two new lines will allow separation of freight and passenger traffic offering significant benefits to both.
One of the most difficult sections of the project is construction of the Rastatt Tunnel where two, about 4km single bores are required to take the new rail lines beneath the Rhine Valley Railway and the Federbach conservation area. Not only is the ground saturated and soil conditions variable, the tunnel is relatively shallow with the overburden ranging from just 3m to 19m. “We have all kinds of ground engineering methods like sheet pile walls and diaphragm walls, bored pile walls, jet grouting, micro-piles, underwater concrete and ground freezing,” says Jörg Steppuhn, technical and contract manager for the Ed Züblin/Hochtief joint venture Tunnel Rastatt.
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
Among this selection of ground stabilisation solutions is an approach that has never been undertaken before, freezing the outer circumferences of the tunnel bores beneath the railway before ploughing through them with the two 10.97m diameter Herrenknecht Mixshield TBMs. “Crossing the Rheintalbahn [Rhine Valley Railway track] it is foreseen to have a ground freezing ring," says Martin Geiger, TBM manager for Züblin. "To produce it two shafts are located at either side of the tracks at a distance of approximately 200m and we have started to drill from that shaft 100m in either direction.”
On site the team are in the process of driving the pipes that will later be frozen. “We are drilling the freeze pipes here,” says Sören Henke, site manager for the ground freezing and other ground engineering works, pointing at the 30m-deep concrete shaft where a ring of 42 drill pipes are being pushed through the ground using horizontal directional drilling. Placed at approximately 950mm centres and 100m long, the pipes will freeze a 2m thick-band around the tunnel and most significantly ensure that the existing railway, which is only approximately 5m above the tunnel crown, is not affected by the passage of the machines. Crucially the railway line is not allowed to close at any time so prevention of settlement is the biggest priority. “It is the most important challenge for the whole project. The overburden is 4-5m and the railway must remain open,” says Geiger.
In fact so cautious is the approach by project client Deutsche Bahn (DB) that as Tunnels & Tunnelling visited the site the HDD rigs were paused as additional monitoring equipment was installed to ensure that this method does not cause any unacceptable movement. “We are waiting to continue as we expect some influence on the tracks from the drilling so we are waiting for the railway to bring a tamping machine in to repair the track if needed. It’s a precaution,” says Geiger emphasising that there has been no damage to the tracks to date.
The decision to use the TBM for such a shallow section was a method recommended by the contractor. “Originally it was foreseen to stop the TBMs and do traditional tunnelling with excavators in the frozen ground but we suggested a technical innovation – to continue with the TBM through the ice, which saved money,” says Steppuhn. This section, which is located at the very end of the tunnel bore to the south of the line, will then involve construction of cut and cover tunnel after the retrieval of the TBM, connecting to a trough section which is already under construction.
US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataNaturally a huge amount of work was undertaken to ensure that this technical innovation would be possible. Thermal and static investigations were conducted by the joint venture to examine the behaviour of the freeze zone. It is crucial that the frozen area remains watertight and that there is no thawing caused by release of thermal energy by the TBMs, or just as importantly that the TBM does not itself become frozen as it passes through the ice. Engineers have devised a range of measures to ensure that this doesn’t happen including reducing the amount of suspension in circulation and using aggregates that are less sensitive to temperature changes. “In the planning phase we even had considered a TBM standstill in the frozen ground to be on the safe side,” says Markus Heimburger, the project manager for Herrenknecht.
The frozen rings are not the only area where cold temperatures are required to protect the ground. At the start of the tunnel to the north of the site, the cover is again very shallow at less than 5m. To prevent blow out and protect the Federbach conservation area a frozen roof structure was created above the tunnel using an array of 770 freeze pipes drilled, on average, 17m deep into the ground above the tube creating a triangle shaped roof along 190m above the east and 290m above the west section of the bore. “We cannot do a normal tunnel drive with the support pressure at the cutter head because we don’t have enough ground above the tube, that means we have to use that construction to anchor the ground above the tube back to the deeper soil,” explains Geiger. It also means that the cutterhead can only be inspected in this area by dropping the bentonite level by one-third the bore diameter of the TBM as the compressed air pressure used to replace the bentonite could otherwise lead to a blowout. So an inspection was carried out before the first machine reached the frozen roof.
This first TBM has undertaken more than 1km of tunnelling with the second about to get underway as Tunnels & Tunnelling visited the project. “Now we are deep enough for a normal tunnel drive without special construction at the surface,” says Geiger.
Other ground freezing measures will be used to support construction of the eight cross passages and protect them from the potential for water ingress due to the high water level at the site. Located every 500m traditional SCL shotcrete lining methods are being used for these connecting tunnels.
But first the team must complete the main bore and below ground a seven-person team led by the contracting joint venture’s project engineer Ursula Wegener, is making good progress in the quaternary gravels heading into the soft tertiary layer with quaternary rocks and cohesive covering layers of sandy clays and silts. The TBM operator is feeling his way forward at around 20mm/min applying 42,000kN of driving force at the face. Pumps are moving bentonite to the face at a flow rate of around 2500m3/hour and each 2m advance takes around two hours. The Mixshield machine has a standard cutting head with an opening ratio of around 30 per cent. “It is all about getting the right balance,” observes Wegener, with the multitude of control screens that tell her and the TBM operator everything about the machine and its relationship with the ground.
One of the challenges that the underground team are facing is the abrasiveness of the ground which means that more inspections and more cutting tools have been required than was originally expected. “The abrasiveness of the ground is influencing the tunnel drive more than expected, we have been surprised at the amount of wear. When we are running we do 16-18m per day but we are having to change cutter tools more often which means standing still for two to four days and this brings the average down,” says Geiger.
For Wegener the abrasive ground also means that her team must inspect the pumping equipment frequently to check for wear on the steel pipes. “Every week we inspect the slurry pipes and we can turn the pipes or place on extra steel if the wear is too much,” says Wegener. Using electromagnetic measurement the team checks that the pipe thickness remains greater than 4mm as maintaining the slurry removal is clearly a critical activity.
Each tunnel ring consists of seven 11.5t segments which are manufactured in Bavaria by Max Bögl and transported by rail to Rastatt station before lorries transport two at a time to the site. The current delivery rate is three trains per week and 23 rings per train. “We are really pleased with the lining quality,” notes Steppuhn.
Launching the second TBM was the next major task for the contractor as Tunnels & Tunnelling visited the site, which was planning to implement its bespoke flying shield start up method which has been used on Crossrail, and the Cologne and Hamburg metros.
“It means pulling the TBM forward instead of pushing it. The main principle of this kind of TBM launch is that the abutment for the TBM’s driving jacks, unlike as the classic thrust frame, automatically advances towards the soft eye wall. This will be done by 24 hollow piston jacks and tension rods which connect the abutment with vertical steel girders at the soft eye wall. Those vertical steel girders then transfer the forces to a concrete beam above the portal and to the concrete slab,” says Geiger.
The second TBM is purposely launched several months behind the first. As the bores are between 17 and 26m apart there is the potential for one bore to affect the other so a staggered start is required.
Unusually for the TBM manufacturer Herrenknecht, which delivers its machines all over the world, the project is conveniently close to their Schwanau headquarters. Development of the two 10.97m machines took around one year.
“For both sides it is an advantage the location being so close. It is easier to provide good and fast support for the job site, and we can bring people to see what we are doing. It is also an emotional thing for people at Herrenknecht – like having it in the family. People are proud of our TBM working so near,” says Heimburger.
Despite the abrasive ground the team is maintaining good progress on the project and is well prepared for the challenge ahead, where the machines will bore through frozen earth just 5m below the existing live railway. Completion of the tunnel bore is scheduled for September with separate contracts for fit out, tracks and M&E works underway until December 2018 at which point the crucial link in Germany’s Trans-European Network will be complete.